Project 1: Foundation Engineering

wall chipping (gypsum ash) 240.00

wall blank base treatment 420.00

door pocket base (Blockboard) 525.00

demolition of brick wall (120 mm) 91.00

light brick wall (120 mm double-sided plastering) 2730.00

painting of openings, beam bottoms and other parts after wall removal 180.00

project 2: Waterway Circuit engineering

strong and weak current construction (lump sum price) 6000.00

waterway construction (lump sum price) 1550.00

change down pipe 222.00

change down pipe 378.00

balcony water outlet 300.00

balcony hot water 300.00

Project III: guest restaurant and aisle

latex paint base layer treatment (putty) 1840.00

latex paint 1104.00

gypsum board flat ceiling 225.00

gypsum board linear light trough ceiling 2376.00

item 4: master bedroom

latex paint base treatment (putty) 980.00

latex paint 588.00

wardrobe cabinet body (ecological board) 4224.00

wardrobe door (ecological board) 313.50

item 5: secondary bedroom

emulsion paint base treatment (puttying) 780.00

emulsion paint 468.00

secondary bedroom 2

emulsion paint base treatment (putty application) 800.00

emulsion paint 480.00

item 6: kitchen

wall tile general specification (300 × 450 < size ≤ 300 × 600) 1083.50

common specification of floor tiles (size 300 × 300) 220.00

kitchen waterproof treatment 270.00

kitchen and sanitary package pipes 169.00

doorway stone paving 25.00

item 7: bathroom

wall tile general specification (300 × 450 < size ≤ 300 × 600) 1375.00

general specification of floor tiles (size 300 × 300) 242.00

toilet backfilling and surface leveling 308.00

toilet waterproof treatment 360.00

kitchen and sanitary package pipes 338.00

hallway stone paving 62.50

toilet sewer protection works 200.00

item 8: balcony

emulsion paint base treatment (batch scraping) 340.00

emulsion paint 204.00

General specification of floor tiles (200 × 200 < size ≤ 800 × 800) 264.00

common specification of wall tiles (300 × 450 < size ≤ 300 × 600) 275.00

balcony handrail base tiling 105.00

balcony waterproof treatment 292.50

masonry guarantee 364.00

Item 9: miscellaneous

materials upstairs fee 300.00

materials transportation fee 300.00

indoor garbage removal fee 300.00

lamp installation 200.00

cleaning appliance installation 150.00

hardware installation 100.00

finished product protection 300.00

Di Gu 300.00

item 10: other charges

third party supervision 1299 00

the service fee of the star foreman is 1000.00

the above is the quotation and details of the decoration of a 91 square meter small three room half package in Wuhan sorted out by Xiaobian for you. You also need to know other decoration knowledge or decoration information. You can enter Wuhan home decoration network to get more information. If you have a house that needs to be decorated, you can enter the decoration bidding page of Wuhan home decoration network to provide you with free door-to-door room measurement service, formulate a plan quotation, and have a reduction or exemption of some decoration funds. See the activity page for details http://whjzw.net/zb/。